1. Transmission Lines Project The transmission line route distance is 105km from Erap to the Mine site. The 132kV single circuit transmission line will pass through Zenag, Bulolo, Wau and eventually to the mine site. HG Power Transmission Sdn. Bhd, a company from Malaysia was awarded the contract to build the transmission line at the cost of K37m.
The transmission line route distance is 105km from Erap to the Mine site. The 132kV single circuit transmission line will pass through Zenag, Bulolo, Wau and eventually to the mine site.
2. Substation Project 132kv switching station at Erap with adequate provision for future development 132kv/11kv switch yard at Hidden Valley Dayen/Pestech JV, a joint venture company from Malaysia and Singapore was awarded the contract to build the two substations at the cost of K26.5m.